Worker’s Ethic

Artist’s Passion

Confidence To Get The Job Done And Counting

Newville Construction’s reputation is built on quality, safety, and on-time completion. We have built our name on trust and reliability. Our knowledge and experience, as well as our commitment to our customers, means choosing Newville Construction guarantees the job is done right.

NCS organizes, manages and maintains civil aspects on projects

  • Keeping projects safe and environmental compliant
  • Communication on project matters
  • Coordination of traffic on a project
  • Organization, documentation, and execution of work on project

Project maintenance & documentation

  • Keeping the job safe and functioning
  • Keeping projects in compliance with state and local regulations
  • Documenting project in compliance with state and local regulations

Project communication

  • Daily plan and progress reporting
  • Highlighted Project #1

    Susquehanna - Jenkins Project

    The following are observations made in the bid / job breakdown process of the Susquehanna – Jenkins Project. From a civil standpoint, the most problematic observation made is the current condition of the roads that have been deemed “existing stabilized access road” per the provided E&S plan. NCS is of the opinion that although most of these roads are currently accessible by standard pick-up trucks, track equipment, and light equipment, they will not withstand the heavy truck traffic necessary to complete a project of this scale. It is the responsibility of NCS to provide this access, then specific roads deemed “existing stabilized access road” must be improved to provide the safe, all weather access roads necessary for the Susquehanna – Jenkins Project to be safe and successful.

    The following are examples of some roadways evaluated and deemed necessary to build by NCS, but marked as “existing stabilized access road.”

    Close

    Access to Structures 7 to 11

    Existing roads need light grading and stone up to Structure 7. The road leading from Structure 7 up to Structure 9 is a steep slope that is eroded and washed out. This road must be built in order to provide concrete truck and crane access. This sloped road cannot be safely traversed by large trucks and cranes in its current condition. Access road from 9 to 11 is in need of light grading and stone in spots.

  • Project: Hooversville Substation 115kv Breaker Replacement

    Hooversville, PA

    Project Owner: Penelec – FirstEnergy
    Construction Management: FirstEnergy
    General Contractor: Newville Construction Services

    Close

    Scope of work, erosion and sediment controls, below grade work, new conduit runs from the replacement of three 115kV breakers to control building. Installation of new pull boxes, demolition of existing foundations and construction of new foundations.

  • Rhodes Lane 500kv Substation

    Smithton, PA

    Project Owner: Tenaska – Westmoreland
    Construction Management: Black & Veatch
    General Contractor: Black & Veatch

    Close

    Site restoration final grading and stoning. Installation of drainage piping, swales and retention ponds. Reconstruct 2.5 miles of site entrance road, road widening, culvert installation, guide rails, water bars, swales and energy dissipaters.

  • Hatfield - Yukon 500kv Loop into Rhodes Lane Substation

    Smithton, PA.

    Project Owner: West Penn Power/ FirstEnergy
    Construction Management: FirstEnergy
    General Contractor: J.W.Didado Electric

    Close

    ROW restoration, grading, slope stabilization, drainage improvements, installation of culverts and swales, seeding.

  • Otter Creek

    East Stroudsburg, PA

    Project Owner: PPL Electric Utilities
    Construction Management: PPL Electric Utilities
    General Contractor: PAR

    Close

    Civil construction, install and maintain environmental and sediment controls, matting, access roads, equipment pads and site restoration.

  • South Akron Transmission Line

    Lancaster Co., PA

    Project Owner: PPL Electric Utilities
    Construction Management: PPL Electric Utilities
    General Contractor: Hinkles & McCoy

    Close

    Civil construction, install and maintain environmental and sediment controls, matting, access roads, equipment pads and site restoration.

  • Archbald - Vardern

    Lackawanna Co., PA

    Project Owner: PPL Electric Utilities
    Construction Management: PPL Electric Utilities
    General Contractor: Harlan Electric

    Close

    Civil construction, install and maintain environmental and sediment controls, matting, access roads, equipment pads and site restoration.

  • Blairsville East Substation 115kv Bus Expansion

    Blairsville, PA.

    Project Owner: Penelec – FirstEnergy
    Construction Management: Welty Co.
    General Contractor: Newville Construction Services

    Close

    Up grades to the existing substation to satisfy a 6 breaker electrical ring bus. Scope of work includes civil work, erosion and sediment controls, foundation demolition and removal, drilled shaft and slab foundation installation, below grade conduit/grounding/trench installation, ground wells and all site work including grading, site restoration, fencing and retention pond installation.

  • Orrtanna Substation Ring Bus Conversion

    Orrtanna, PA.

    Construction Management: Burns & McDonnell
    General Contractor: Newville Construction Services

    Close

    Scope of work involves civil work, foundation demolition and removal, drilled shaft and slab
    foundation installation, below grade conduit/grounding/trench installation, and all site work including
    grading and site restoration.

  • Niles Valley to Wellsboro 115kv Transmission Line

    Niles Valley, PA. - Wellsboro, PA

    Project Owner: Penelec – FirstEnergy
    Construction Management: Burns & McDonnell
    General Contractor: Newville Construction Services

    Close

    Provide below grade construction scope of work for the 6.1 mile Niles Valley Wellsboro 115 kv Transmission Line. Install 27 anchor bolt large diameter drilled shaft foundations, install 75 direct embed monopole drilled shafts, temporary pad mount foundation, trenching and conduit, install trench and vault for underground distribution relocation.

Recent Projects

Peckville: Varden 69ky replacement project / 14 miles of transmission line Northeast of Scranton, PA / PPL project / Kenny Construction / Harlan Electric

Pocono: Paupack Transmission line Project / PPL project / Kenny Construction

Riverdale: Butler Transmission Line / JCP&L project / Didado

Osage to Collins Ferry West Virginia for Mon Power

Collins Ferry to West Run West Virginia for Mon Power

Homer City to Handsome Lake Pennsylvania for Allegheny Power

Rocktown Loop New Jersey for PSE&G

Clients Currently Served

  • Burns & McDonald
  • Harlan Electric
  • Hinkles & McCoy
  • IB Abel Electric
  • JCPL/ FirstEnergy
  • JW Didado Electric
  • Met Ed/ FirstEnergy
  • Michels Corporation
  • MJ Electric
  • Mon Power/ FirstEnergy
  • National Grid
  • New Enterprise Stone & Lime
  • NYPA
  • PADOT
  • PAR Electrical Contractors
  • Penelec/ FirstEnergy
  • Penn Power/ FirstEnergy
  • PPL
  • PSEG
  • Riggs Distler
  • Toledo Edison/ FirstEnergy
  • West Penn Power/ FirstEnergy